Calafat — Equipment Price Benchmark: the held prices vs the 2026 market

11 August 2026 · basis: as-drawn plant (7,31 MWp AIKO 775 ABC + 16 MWh LFP, pair) · produced by a 5-researcher + 2-adversarial-auditor workflow (~210 sources checked; raw archive model/price_research_s13_raw.json) · all € ex-VAT unless stated

1 · The verdicts (audited)

ItemHeld priceMarket band, Aug 2026 (verified)Verdict
All-in solar EPC (7,31 MWp fixed-tilt RO, ABC modules, turnkey incl. MV/PTAB stations + 20 kV route, ex-DSO tariff)€445k/MWp DC
(settled in writing)
€420–500k/MWp; retender €420–470k. Anchor comp: Electrica Satu Mare 3, Jun 2026 — €446k/MWp at 62,5 MWp INCLUDING a 110 kV substation + 3 yrs O&MFAIR — mid-band, not generous. The lever is SCOPE, not the unit price
BESS 16 MWh (2×8 MWh, supply + install + commissioning, ex-MV trafo/grid) €150/kWh (€2,4M)
(not finally negotiated)
€135–175/kWh at this order size; sharp competitive retender €130–150. Comp: OMV Gabare 600 MWh full-scope €167/kWh (FID Jun 2026) FAIR — mid-band. Recoverable ≤ ~€160k, and shrinking (see §3 timing)
— module line inside the EPC≈ €125–130/kWp impliedABC project DDP €0,115–0,125/Wp (the BC-over-TOPCon premium narrowed to $0,003–0,005/W FOB — OPIS Jun 2026) slightly OVER inside the bundle — €40–90k headroom + the supply-channel question (§3)
— ABC → mainstream TOPCon swapsaving only +€0,008–0,020/Wp ≈ €60–150k small lever; the AIKO panel is worth keeping if the price holds
— inverters (16 × ~350 kW)inside EPC€17–21/kW → €95–118k plant lot for scope math
— PTAB/MV block as drawn (6–8 × 1600 kVA + cells + 2×230 m cable)inside EPC €405–960k, mid ≈ €633kprice OK — but 9,6–12,8 MVA of stations also serves the BESS: watch the allocation in any scope dispute

2 · What the adversarial audit corrected (why these bands are trustworthy)

3 · Timing + negotiation implications

4 · Key comps (audited)

DealDateSizeImplied priceNotes
Electrica / New Trend — Satu Mare 3Jun 202662,5 MWp€446k/MWp ex-VAT, incl. 110 kV station + 3 yr O&M — the anchor
Electrica / Foton — Bihor 1May 202678,8 MWp + 18 MWh€464k headline; ~€410–430k net of BESS incl. 110 kV + BESS + O&M
Astor Enerji → Enexus, Alba IuliaMay 202675 MWp€440k/MWpex-220 kV station; Turkish owner
Hidroelectrica / Enevo — BrăilaMay 202645,9 MWp~€650k/MWp (corrected)incl. 110 kV; state buyer premium
Ameresco/SUNEL — Rovinari+TismanaApr 2025466 MWp€651k/MWpbrownfield coal land, incl. O&M
OMV Petrom — Gabare BESSJun 2026600 MWh€167/kWhfull-scope utility EPC, GWh-class
Rezolv — Dama Solar2025–261.238,9 MWp DCall-in 0,54–0,57 €/Wpfull project incl. dev/grid — scale floor
Bands carry each source's basis (EXW/FOB/DDP/installed · DC/AC · VAT) in the raw archive — model/price_research_s13_raw.json holds every figure with its URL. Key indices: pvXchange Jul 2026 · OPIS/pv-magazine Jun–Jul 2026 · BNEF Dec 2025 storage survey · ess-news Apr–May 2026 · CNESA H1 2026 · Electrica/Ameresco/OMV award disclosures. Prepared by Claude for Roya · 11 Aug 2026 · D70. INTERNAL.